File #: 23-0038    Version: 1 Name:
Type: Report Status: Passed
File created: 1/12/2023 In control: Public Infrastructure Committee
On agenda: 1/16/2023 Final action: 1/16/2023
Title: Report of Board of Public Works of 12/21/2022 for 4th & final payment $9,041.02 to Vinton Construction Company for 2022 Intersection Reconstruction for Two-Way Traffic, WS-22-13; recommending payment
Attachments: 1. WS-22-13 Final Payment

Title

Report of Board of Public Works of 12/21/2022 for 4th & final payment $9,041.02 to Vinton Construction Company for 2022 Intersection Reconstruction for Two-Way Traffic, WS-22-13; recommending payment