7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg
Aye:
6. Change Orders
City Clerk submitted the following one (1) change order for approval:
Lunda Construction, CO#10 for Manitowoc Marina Dock Replacement
Project, WO-24-22, ($8,400.03)
A motion was made by Nycz, seconded by Alfred, that these change orders be
approved. The motion carried by the following vote:
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg
Aye:
7. Pay Estimates, Various Engineering/Public Works Projects
City Clerk submitted the following City Engineer's estimates for approval
and payment:
Strand Associates, Design of Rubick Field Dry Detention, Project
#3516.036, Est. 17, $31,100.00
Ayres Associates, Inc., STH 42 Sanitary Sewer Replacement, Project
#45-0596.70, Est. 5, $3,866.99
Strand Associates, South 19th Pumping Station, Project #3516.033,
Est. 26, $12,475.78
A motion was made by Nycz, seconded by Reckelberg, to approve the payments.
The motion carried by the following vote:
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg
Aye:
8. Contractor's Payroll Affidavits
None
Appeal from Property Owner for Snow Removal Assessment
Property owner appeal for snow removal assessment at parcel 836-301-010
Property owner was not present.
Moved by Nycz, seconded by Koski, to deny the appeal. The motion carried by
the following vote:
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg
Aye:
Aye:
9. Adjournment
A motion was made by Nycz, seconded by Reed, that this meeting be adjourned
at 4:08 p.m. The motion carried by the following vote:
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg