A motion was made by Nycz, seconded by Beeman, to refer the quote to the
Director of Public Infrastructure for tabulation and recommendation. The motion
carried by the following vote:
7 - Koski, Reed, Alfred, Nycz, Norell, Beeman and Reckelberg
Aye:
5. Agreement with Luisier Plumbing for Citizen Park Irrigation for a contract price of
$14,362.00, AGMT-25-09
A motion was made by Nycz, seconded by Beeman, that this agreement be
approved. The motion carried by the following vote:
7 - Koski, Reed, Alfred, Nycz, Norell, Beeman and Reckelberg
Aye:
6. Change Orders
City Clerk submitted the following six (6) change orders for approval:
Lunda Construction, CO#9 for Marina Dock Replacement, WO-24-22,
$25,961.60
Vinton Construction Company, CO#1 for 2024 S 19th Street Pumping
Station Rehabilitation, WU-24-10, $8,419.00
Brickline Inc., CO#1 & Final for 2025 Epoxy Painting - Pavement
Marking Program, WS-25-9, $156.55
Vinton Construction Company, CO#2 for 2025 Concrete Paving
Program, WS-25-1, $1,190.00
Vinton Construction Company, CO#1 for 2025 Asphalt Paving
Program, WS-25-4, $3,776.00
Vinton Construction Company, CO#2 for 2024 Water Main Extension,
WU-24-21, $56,602.00
A motion was made by Nycz, seconded by Beeman, that these change orders be
approved. The motion carried by the following vote:
7 - Koski, Reed, Alfred, Nycz, Norell, Beeman and Reckelberg
Aye:
7. Pay Estimates, Various Engineering/Public Works Projects
City Clerk submitted the following City Engineer's estimates for approval
and payment:
Interstate Improvement, Inc., 2025 Continuous Diamond Grinding,
WS-25-12, Est. 1 & Final, $240,275.00
Brickline Inc., 2025 Epoxy Pavement Marking Program, WS-25-12, Est.
1 & Final, $131,771.60
Vinton Construction Company, 2025 Concrete Paving I, WS-25-1,
Est. 4, $479,114.88