3. Change Orders  
City Clerk submitted the following four (4) change orders for approval:  
Vinton Construction Company, CO #4 & Final for 2023 River Point  
Phase II, WS-23-2, ($71,929.84)  
Vinton Construction Company, CO #2 & Final for 2024 Asphalt Paving  
II Alleys, WS-24-2, $28,759.65  
Vinton Construction Company, CO #3 & Final for 2024 Concrete  
Paving Program, WS-24-1, $42,920.05  
Vinton Construction Company, CO #2 for 2024 Concrete Paving  
Program, WS-24-1, $5,626.46  
A motion was made by Nycz, seconded by Reckelberg, that these change orders  
be approved. The motion carried by the following vote:  
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg  
Aye:  
4. Pay Estimates, Various Engineering/Public Works Projects  
City Clerk submitted the following City Engineer's estimates for approval  
and payment:  
Boardt Electric Service, Inc., Traffic Signals DOT SISP II (S 21st &  
Washington Street), WS-24-12, Est. 1, $164,286.96  
J Miller Electric Inc., Senior Center Generator, WO-23-20R, Est. 3,  
$50,551.40  
RA Smith, Newton Gravel Pit Water Main Extension Phases 2-3, Est. 14,  
$865.00  
Vinton Construction Company, Concrete Slab Replacement,  
WS-24-14, Est. 3, $123,385.27  
Vinton Construction Company, South 19th Street Pumping Station  
Rehabilitation, WU-24-10, Est. 2, $80,750.00  
Vinton Construction Company, Bayshore Trail Project, WS-24-18, Est.  
2, $292,746.78  
Vinton Construction Company, Buffalo & Chicago Streetscape,  
WS-24-23, Est. 1, $94,777.20  
Vinton Construction Company, Asphalt Paving II Alleys, WS-24-4, Est.  
2 & Final, $47,534.40  
Vinton Construction Company, 2024 Concrete Paving I, WS-24-1,  
Est. 4 & Final, $143,274.16  
Vinton Construction Company, 2023 River Point Development Phase  
II, WS-23-2, Est. 11 & Final, $139,155.92  
A motion was made by Nycz, seconded by Norell, to approve the payments. The  
motion carried by the following vote:  
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg  
Aye:  
5. Contractor's Payroll Affidavits  
None  
2. Property owner appeal for noxious weed cutting assessment  
Request to rescind noxious weed cutting assessment for property at 1015  
Dewey St.  
Moved by Nycz, seconded by Reed, to deny the request. The motion carried by  
the following vote:  
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg  
Aye:  
6. Adjournment  
A motion was made by Nycz, seconded by Norell, that this meeting be adjourned  
at 4:06 p.m. The motion carried by the following vote:  
7 - Nickels, Koski, Reed, Alfred, Nycz, Norell and Reckelberg  
Aye:  
Mackenzie Reed  
City Clerk