Report of Board of Public Works of 8/3/2022 for 5th and Final payment of
$65,861.12 to Vinton Construction Company for Camp Vits Parking Lot & Trail,
WS-21-24; recommending payment
Attachments:
Report of Board of Public Works of 7/6/2022, of bids received for Manitowoc
City Hall Re-Roofing Project, WB-22-21; recommending awarding base bid to
low bidder, Crafts Inc, in the amount of $179,361.00
Attachments:
Report of Board of Public Works of 7/6/2022, of bids received for New PVC
Re-Roofing System at Manitowoc Public Library, WB-22-22; recommending
awarding alternate 1, in the amount of $225,543.00
Attachments:
Report of Board of Public Works of 8/3/2022, of bids received for Playground
Equipment for Parks - Rebid, WB-22-20R; recommending awarding to low
bidder, Lee Recreation, in the amount of $113,731.00
Attachments:
Report of Board of Public Works of 8/3/2022, of bids received for Lincoln Park
Tennis Court Resurface Project, WS-22-24; recommending awarding to low
bidder, Munson Inc., in the amount of $53,719.00
Attachments:
Report of Board ofPublic Works of 7/20/2022 of approval to enter into
AGMT-22-12 with McMullen & Pitz Construction Company for repairs to the
sheet pile cap east of Bud Tower - Manitowoc Harbor for a contract price of
$16,400.00; recommending acceptance of report and place on file
Attachments:
Report of Board of Public Works of final payments to contractors for
agreements under $25,000.00; recommending acceptance and place on file
Attachments:
Report of Quotes received for QE-22-5 Mobile 4 Column Lift System with
Remote Control, QE-22-6 Heavy Duty Truck Wheel Balancer, QE-22-7 Rotary
Heavy-Duty Tire Changer; recommending approval to US Petroleum Equipment
for the three quotes received
Attachments:
7. Public Safety Committee (Consent)
Police Department request for special distribution from the City of Manitowoc
K-9 Preservation Fund, recommend to approve the request.
Attachments: